Waterproofing the floor of a balcony
by Manuel G. Bl�zquez
If you have damp coming in from your balcony, be it of cement, concrete or tiled, a simple and cheap improvement job using elastic-based anti-damp paints will solve the problem. If the deterioration is serious, the solution will have to be a complete renovation of the flooring and the installation of bituminous or plastic planks between the base of the flooring and the finish.
�
Tools and materials
Metallic brushes to clean and repair the joints; trowel, cement, sand and water for partial repairs of the surface; brushes and rollers to apply the waterproof paint. Masonry tools for the new flooring and tiling.�
�
State of the surface
o�Before proceeding to waterproof a balcony which is already floored, the state of the paving should be checked. �
o Check to see if there are any unsealed joints between the tiles. Also make sure there
are no broken or loose tiles.
o�Check the wall and drain joints for cracks.�
o If necessary, repair the above with suitable products and using the right methods.
o�If the surface is cement, make sure there are no loose parts.
�
Layer of insulation paint
o�If the balcony is not going to be practical, the waterproofing solution is very easy.�
o Clean dust and all work remains from the surface. It should also be dry.�
o With a large brush or roller extend a layer of waterproof rubber paint. This product dries up on contact with damp and its elasticity prevents water from passing through. Do not forget joints and at a 10 centimetre distance to walls to guarantee perfect waterproofing in all parts.
o�Leave to dry for 24 hours before passing a second hand of paint in a perpendicular direction to the first.�
o It is advisable not to use very hot or cold paint, or paint when it is raining or threatening to rain.�
o The thickness of the layer of paint should be at least 1.5 mm. If not, repeat. Wait at least 48 hours before stepping on the surface.
o�Better insulation is achieved by placing a fibre glass or synthetic board before applying the last layer of waterproofer.
�
Waterproofing boards
o�If a balcony is going to be used a lot by the inhabitants of the house or a new floor is
going to be laid, a bituminous or plastic plank at least 2.5mm thick should be installed.
o�After installing the floor base and before adding the finish, tiles or other, place the waterproofing board, taking care that it extends at least 10 cm from each to guarantee
the insulation of the joints.
o�Install a new base on the insulating board ready for the new tiles or finish.
�

Contact us  -  ï¿½ Repsol YPF 2001-2004  -  Legal Notice
Benefits of
the portal
Products
and services
All about
Repsol YPF
Welcome to
infinity
Get a free large capacity e_mail account

Personalize your computer